Rio Tinto issues update on Tropical Cyclone Veronica

Published by , Editor
Global Mining Review,


Rio Tinto’s iron ore operations in the Pilbara, Western Australia, are progressively resuming following the passing of Tropical Cyclone Veronica.

However, initial inspections uncovered some damage to the Cape Lambert A port facility. As a result, Rio Tinto has declared force majeure on certain contracts and is working with its customers to minimise any disruption in supply.

The impact of the disruption to production caused by the cyclone and repairing the damage sustained at the port facilities, combined with the damage caused by the fire at Cape Lambert A in January, will result in a loss of approximately 14 million t of production in 2019. As a result, Rio Tinto’s Pilbara shipments in 2019 are expected to be at the lower end of the 338 million t and 350 million t (100% basis) guidance provided.

Safety remains the company’s top priority as it ramps up operations and undertakes the necessary remediation work, following the passing of the cyclone.

Read the article online at: https://www.globalminingreview.com/trade-transport/01042019/rio-tinto-issues-update-on-tropical-cyclone-veronica/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 
 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Australian mining news