Skip to main content

Nevada Copper signs mining development contract with SMD

Published by , Editorial Assistant
Global Mining Review,


Nevada Copper Corp. has provided additional details on the previously announced award of a 66 000 ft underground lateral development contract with US-based Small Mine Development. SMD began mobilisation activities on May 10, 2023.

Randy Buffington, President and CEO, commented: “We are very pleased to award this contract to SMD, who have a strong reputation for safe and productive development in Nevada hard rock mines. Partnering with SMD is an effective way to ensure we have the ore stopes available to achieve and maintain our planned steady state production rate of approximately 5 000 tpd.”

Key Components of Development Contract

  • 66 000 ft of lateral capital development over a 24-month contract period.
  • Delivery of fully developed ore stopes in 2023 to restart and maintain nameplate milling operations (approximately 5000 tpd).
  • Unit rate agreement for development and associated services to align SMD and Nevada Copper for success on this key restart deliverable. Nevada Copper will self-perform stope mining in addition to managing ore and waste handling and underground stope ground support services, allowing each group to focus within their specific expertise.

Development and Capital Projects Progress

The company has either substantially completed or well advanced various debottlenecking projects that were previously defined as key for a successful ramp-up to steady state, including:

  • Construction of the vent shaft is complete, and the surface fans have been commissioned.
  • Ore pass 2 rehabilitation is complete, increasing materials handling flexibility and decreasing material re-handle.
  • Vertical excavation of the coarse ore bin is complete, and excavation of the conveyor drift is in progress.
  • Underground electrical infrastructure is in place to support the development contractor’s ventilation requirements.
  • A key ventilation raise in the 2798 level is in progress and expected to be completed by the end of May 2023. This ventilation raise is critical to providing air circulation to all active areas of the mine.
  • Installation of the monorail is complete for the underground dewatering system (Geho project).
  • Ongoing lateral development is well advanced beyond the first and second dike crossings into the EN Zone and continues to demonstrate competent ground conditions, as anticipated by the model.
  • Non-critical path third dike crossing continues to be advanced with completion planned in 2Q23.

Read the article online at: https://www.globalminingreview.com/mining/23052023/nevada-copper-signs-mining-development-contract-with-smd/

You might also like

 
 

Embed article link: (copy the HTML code below):