Skip to main content

Coal production at TIG’s Project F commences 

Published by , Editor
Global Mining Review,


First  coal  has  been  mined  and  trucked from Tigers  Realm  Coal’s (TIG) Project F to the coal stockpiles at the TIG owned Beringovsky Port in Russia.

      

Following the successful rights issue to shareholders raising US$23.3 million, TIG commenced development works in early August. During a four and a half month period, TIG completed construction of its winter road from the pit to the port, and constructed the site workshop, office, camp upgrades and an analytical laboratory. Additional mining and coal haulage equipment was procured and delivered to the site, and key workforce recruited primarily from the local community and Far East Russia.

In less than four years, TIG has progressed Project F on the Amaam North Licence from resource identification and initial evaluation to production. This achievement is the result of the consistent support of its shareholders, together with the hard work and commitment of its employees.

Coal mining has commenced in a part of the pit where the waste to coal stripping ratio for the first 12 months of production is less than 2:1 (bcm waste : tonne coal). Mining is being carried out with a fleet comprising a 40 t excavator on coal, a 70 t excavator on waste, five 40 t in pit trucks, a grader and two70t tracked dozers. Coal haulage on the winter road from the pit to the port is being undertaken with eight 30 t capacity Scania trucks.

TIG plans to mine and haul coal to Beringovsky port on the winter road until early May. At that time, coal production will temporarily cease and road works will recommence to convert the winter road into an all season road. Following the completion of these works in Q3, coal mining and trucking to the port will recommence at rate of 600 000 tpy.

TIG’s coal sales forecast for the unwashed product in 2017 are estimated at 30 000 t of semi- soft coking coal (SSCC) to the steel sector and up to 220 000 t of thermal coal into the industrial and power generation sector. The 1Q17 SSCC settlement is US$171/t FOB, and the current Newcastle thermal price is approximately US$85/t - basis 6000 kcal/kg NAR.

Phase one of Project F is the first stage of a development plan ,which builds to a 2 million tpy opencast operation which, on the completion of construction of a washing plant, will predominantly produce a semi- hard coking coal (SHCC). 1Q17 hard coking coal (HCC) settlement is US$285/t FOB. TIG’s SHCC, which will be produced post completion of the wash plant, would be expected to sell at an approximate 15 to 20% discount to the HCC price.

Read the article online at: https://www.globalminingreview.com/mining/20122016/coalproductionattigs-projectfcommences/

You might also like

 
 

Embed article link: (copy the HTML code below):