Skip to main content

Rio Tinto satisfies conditions for development of Guinea iron ore deposit

Published by , Editorial Assistant
Global Mining Review,


All conditions have now been satisfied for Rio Tinto’s investment to develop the Simandou high-grade iron ore deposit in Guinea, including the completion of necessary Guinean and Chinese regulatory approvals. The transaction is expected to complete during the week of 15 July 2024.

Along with the recent approval by the Board of Simfer, this allows Simfer to invest in and fund its share of co-developed rail and port infrastructure being progressed in partnership with Winning Consortium Simandou (WCS), Baowu and the Republic of Guinea.

More than 600 km of new multi-use trans-Guinean railway together with port facilities will allow the export of up to 120 million tpa of mined iron ore by Simfer and WCS from their respective Simandou mining concessions in the southeast of the country. Together, this will be the largest greenfield integrated mine and infrastructure investment in Africa.

Rio Tinto Executive Committee lead for Guinea and Copper Chief Executive Bold Baatar said: “We thank the Government of Guinea, Chinalco, Baowu and WCS for their partnership in reaching this milestone towards developing the world class Simandou project.

“Simandou will deliver a significant new source of high-grade iron ore that will strengthen Rio Tinto’s portfolio for the decarbonisation of the steel industry, along with trans-Guinean rail and port infrastructure that can make a significant contribution to the country’s economic development.”

Under the terms of the transaction, Simfer will acquire a participation in the WCS project companies constructing rail and port infrastructure, commit to perform a portion of the construction works itself and commit to funding its share of the overall co-developed infrastructure cost, in an aggregate amount of approximately US$6.5 billion (Rio Tinto share approximately US$3.5 billion).

Chalco Iron Ore Holdings Ltd (CIOH) has now paid its share of capital expenditures incurred or required by Simfer to progress critical works up to completion. A first payment of approximately US$410 million, for expenditures until the end of 2023, was made on 28 June 2024, and a second payment of approximately US$575 million, for 2024 expenditures, was made on 11 July 2024. These amounts settle all expenditures incurred up to date.

The co-developed infrastructure capacity and associated cost will be shared equally between Simfer, which will develop, own and operate a 60 million tpa mine in blocks 3 and 4 of the Simandou Project, and WCS, which is developing blocks 1 and 2.

Under the co-development arrangement, Simfer and WCS will deliver separate infrastructure scopes to leverage expertise. Simfer will construct the approximately 70 km Simfer spur rail line and a 60 million tpa transhipment vessel (TSV) port, while WCS will construct the dual track approximately 536 km main rail line, the approximately 16 km WCS spur rail line and a 60 million tpa barge port.

Once complete, all co-developed infrastructure and rolling stock will be transferred to and operated by the Compagnie du Transguinéen (CTG) joint venture, in which Simfer and WCS each hold a 42.5% equity stake and the Guinean State a 15% equity stake.

First production from the Simfer mine is expected in 2025, ramping up over 30 months to an annualised capacity of 60 million tpa (27 million tonnes Rio Tinto share). The mine will initially deliver a single fines product before transitioning to a dual fines product of blast furnace and direct reduction ready ore.

Read the article online at: https://www.globalminingreview.com/mining/18072024/rio-tinto-satisfies-conditions-for-development-of-guinea-iron-ore-deposit/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Rio Tinto news African mining news Iron ore mining news