Skip to main content

Rio Tinto issues update on Oyu Tolgoi underground project

Published by , Editor
Global Mining Review,


Rio Tinto is providing an update on the schedule and cost of the Oyu Tolgoi underground project in Mongolia.

The project continued to progress in 2019 towards its path to become one of the largest copper mines in the world.

Since February, key below ground infrastructure such as the control room facility and the jaw crusher system are now complete and construction of shafts 3 and 4 is progressing well. The commissioning of shaft 2 remains on track for October 2019.

As previously advised, enhanced geotechnical information and data modelling suggests that there may be some stability risks identified with the approved mine design and so a number of other mine design options are also under consideration to complete the project. Studies to date indicate that these options may result in some of the critical underground infrastructure, such as the mid-access drive and the ore handling system, being relocated or removed. Options relating to the sequence of crossing the panel boundaries during mining operations are also being analysed.

These options are being evaluated to determine the final design of the first panel of mining, ‘Panel 0’, and this work is anticipated to continue until early 2020. Given the further technical work which is needed, the definitive estimate, which will include the final estimate of cost and schedule for the remaining underground project, is now expected to be delivered in the second half of 2020, reflecting the preferred mine design approach.

All options under consideration present a pathway to sustainable first production, and have different cost and schedule implications. To date, these have been defined to a level of accuracy associated with a conceptual study or order of magnitude study, and, therefore, significantly more work is required to complete the final assessment.

Preliminary information now suggests that, depending on which mine design options are adopted, first sustainable production could be achieved between May 2022 and June 2023, a delay of 16 - 30 months compared to the original feasibility study guidance in 2016. This range includes contingency of up to eight months reflecting the unexpected and challenging geotechnical issues, complexities in the construction of shaft 2 and the detailed work still required to reach a more precise estimate.

Preliminary estimates for development capital spend for the project, depending on the outcome of the work described above, is now US$6.5 billion to US$7.2 billion, an increase of $1.2 billion to $1.9 billion from the US$5.3 billion previously disclosed.

These preliminary ranges incorporate a range of productivity assumptions and remain subject to change prior to completion of the definitive estimate.

The company will continue to focus on minimising the impact to project schedule and cost, as it works through the detailed analysis and testing of each mine design option. Although further work is necessary to reach definitive conclusions, Rio Tinto is reviewing the carrying value of its investment in the project and will announce if any changes are required, in the half year results on 1 August 2019.

Stephen McIntosh, Group Executive, Growth & Innovation, said: “We have made significant progress on a number of key elements in the construction of the underground project during 2019. However, the ground conditions are more challenging than expected and we are having to review our mine plan and consider a number of options. Delays are not unusual for such a large and complex project but we are very focused as a team on finding the right pathway to deliver this high value project.”

Arnaud Soirat, Chief Executive, Copper & Diamonds, said: “Oyu Tolgoi is a world-class ore body and a world-class business that is already producing copper, employing around 16 000 people and benefitting Mongolia through taxes, royalties and significant procurement. We are working with TRQ and the Government of Mongolia to complete the underground, which will unlock the most valuable part of the mine for the benefit of all stakeholders.”

Read the article online at: https://www.globalminingreview.com/mining/17072019/rio-tinto-issues-update-on-oyu-tolgoi-underground-project/

You might also like

EMI

Electrification in Mining virtual conference

Join us on 16 April 2024 for Global Mining Review's first Electrification in Mining event is an interactive virtual conference, focusing on electrification as the future of sustainable mining and exploring the innovative approaches and technologies being developed to facilitate its implementation.

Register for FREE »

 

An Ecosystem For All

Komatsu USA presents a framework for what an open, democratic, and interoperable ecosystem for the mining industry – that leverages technology – might look like.

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Rio Tinto news Copper mining news


 

Global Mining Review is not responsible for the content of external internet sites.