BHP has approved US$5.7 billion (CAN$7.5 billion) in capital expenditure for the Jansen Stage 1 (Jansen S1) potash project in the province of Saskatchewan, Canada.

BHP CEO, Mike Henry, said Jansen is aligned with BHP’s strategy of growing our exposure to future facing commodities in world class assets, which are large, low cost and expandable.

“This is an important milestone for BHP and an investment in a new commodity that we believe will create value for shareholders for generations,” Henry said.

Jansen is located in the world’s best potash basin and is expected to operate up to 100 years. Potash provides BHP with increased leverage to key global mega-trends, including rising population, changing diets, decarbonisation and improving environmental stewardship.

“In addition to its merits as a stand-alone project, Jansen also brings with it a series of high returning growth options in an attractive investment jurisdiction. In developing the Jansen project, BHP has had ongoing positive engagement and collaboration with First Nations and local communities, and with the provincial and federal governments. Jansen is designed with a focus on sustainability, including being designed for low greenhouse gas (GHG) emissions and low water consumption,” Henry added.

Jansen S1 is expected to produce approximately 4.35 million tpy of potash, and has a basin position with the potential for further expansions (subject to studies and approvals). First ore is targeted in the 2027 calendar year, with construction expected to take approximately six years, followed by a ramp up period of two years.

Jansen S1 includes the design, engineering and construction of an underground potash mine and surface infrastructure including a processing facility, a product storage building, and a continuous automated rail loading system. Jansen S1 product will be shipped to export markets through Westshore, in Delta, British Columbia, and the project includes funding for the required port infrastructure.

BHP anticipates that demand growth will progressively absorb the excess capacity currently present in the industry, with opportunity for new supply expected by the late 2020s or early 2030s. That is broadly aligned with the expected timing of first production from Jansen. Beyond the 2020s, the industry’s long run trend prices are expected to be determined by Canadian greenfield solution mines. In addition to consuming more energy and water than conventional mines like Jansen, solution mines tend to have higher operating costs and higher sustaining capital requirements.

At consensus prices, the go-forward investment on Jansen is expected to generate an internal rate of return of 12 – 14%, an expected payback period of seven years from first production and an underlying EBITDA margin of approximately 70% given its expected first quartile cost position.

The company have previously acknowledged the US$4.5 billion (pre-tax) of capital invested to date has resulted in a significant initial outlay and that the approach would be different if considering the project again today. The investment to date includes construction of the shafts and associated infrastructure (US$2.97 billion scope of work), as well as engineering and procurement activities, and preparation works related to Jansen S1 underground infrastructure. The construction of two shafts and associated infrastructure at the site is 93% complete and expected to be completed in the 2022 calendar year. To date approximately 50% of all engineering required for Jansen S1 has been completed, significantly de-risking the project. If the investment to date were to be included, the full cycle project would yield a much lower internal rate of return.

As part of its 2021 financial results, the company have assessed the carrying value of the existing potash asset base as at 30 June 2021 and have recognised a pre-tax impairment charge of US$1.3 billion (US$2.1 billion after tax). The impairment charge against the potash assets reflects an analysis of recent market perspectives and the value that we would now expect a market participant to attribute to the investments to date.

Read the article online at: https://www.globalminingreview.com/finance-business/18082021/bhp-approves-jansen-stage-1-potash-project-investment/