Samarco funding – restart preparation

Published by , Editorial Assistant
Global Mining Review,


BHP has approved US$44 million for BHP Billiton Brasil’s share of funding for work related to the restart of one concentrator at Samarco Mineração S.A.’s operations at its Germano complex in Minas Gerais, Brazil. Samarco’s operations were suspended following the failure of the Fundão dam on 5 November 2015.

The funding will enable the construction of a filtration plant over the next 12 months and the commencement of operation readiness activities for restart.

On 25 October 2019 the Mining Activities Chamber of the State Council for Environmental Policy in Minas Gerais, Brazil, granted the corrective operating licence for Samarco’s operating activities at its Germano Complex.

Samarco has now obtained all environmental licenses required to progress towards operational restart. Restart can occur when the filtration system is complete and Samarco has met all necessary safety requirements, and will be subject to final approval by Samarco’s shareholders.

BHP Billiton Brasil Ltda. and Vale S.A. each hold a 50% interest in Samarco.