Mexus making progress at Santa Elena mine
Published by Stephanie Roker,
Editor
Global Mining Review,
Mexus Gold US confirmed and restated that continuous leaching continues on its 5000 t heap leach pad. The returning solution from pad #1 continues to increase in values and flow.
Mexus expects the returns to stabilise in the next few days allowing for the gold extraction process to begin. The loading of an additional 5000 t of mineralised material on pad #2 will be completed by the end of the week.
The leaching of pad #2 will commence once returns from pad #1 peak. The company will have continuous flow from approximately 10 000 t of material on pads 1 and 2 with grades expected to reach 4.5 g/t gold.
The mining of an additional 5000 t of mineralised material has already begun and will be ready to place on pad #1 when leaching moves to pad #2.
Read the article online at: https://www.globalminingreview.com/exploration-development/10092019/mexus-making-progress-at-santa-elena-mine/
You might also like
Vema Hydrogen and First Atlantic Nickel & Cobalt sign LOI to develop engineered mineral hydrogen at Pipestone XL Awaruite Project in Newfoundland
Vema Hydrogen has announced that it has entered into a non-binding Letter of Intent (LOI) with First Atlantic Nickel & Cobalt Corp, to jointly develop Engineered Mineral Hydrogen (EMH) at the Pipestone XL project, a 30 km ultramafic belt in central Newfoundland.