OceanaGold receives final permit for Haile Gold Mine expansion
Published by Joe Toft,
Editorial Assistant
Global Mining Review,
In addition, the South Carolina Department of Health and Environmental Control (DHEC) issued the mine operating permit (MOP) on 14 December 14 2022, which, following a statutory 15-day period, will become final and will complete the state permitting process for the Haile expansion.
OceanaGold President and CEO, Gerard Bond, said:
"The receipt of the Haile SEIS ROD and the MOP represents a significant milestone for OceanaGold, putting the company on a clear path to deliver increased gold production and lower unit costs at this cornerstone asset. We are thrilled to be progressing the next stage of Haile's growth as we expand our operations underground and, with exploration success, pursue further opportunities to profitably extend the mine life."
The receipt of the SEIS ROD, 404 Permit and the MOP allows for development and operation of the underground mine and an expansion of the operating footprint to allow for additional waste containment facilities and expanded tailings storage capacity.
With the early works program approved in 3Q23, underground development of the main production decline and exhaust ventilation portals is safely progressing in-line with plan. First ore from the Haile underground remains on-track for delivery in 4Q23.
Read the article online at: https://www.globalminingreview.com/mining/21122022/oceanagold-receives-final-permit-for-haile-gold-mine-expansion/
You might also like
CIM introduces Innovation and Technology Society to drive industry competitiveness
The Innovation & Technology Society (ITS) was recently launched at CIM CONNECT in Montreal to unite innovators and companies across the mining value chain.