Rio Tinto hits milestone at Oyu Tolgoi
Published by John Williams,
Editorial Assistant
Global Mining Review,
Rio Tinto has achieved a significant milestone at the Oyu Tolgoi mine in Mongolia with the completion of Shaft 2, which enables the acceleration of work on the underground development.
Shaft 2, a 10 m dia. shaft sunk to approximately 1.3 km below the surface, has now entered into the final stages of commissioning.
This is a critical piece of infrastructure and will enable a step change in terms of delivering the underground mine. Shaft 2 can carry 300 people per cage cycle versus a maximum of 60 people per cage cycle through Shaft 1.
The 48 t capacity cage can now be used to support logistics, transporting supplies and components for development of the mine.
Stephen McIntosh, Group Executive, Growth and Innovation said: "This is an important milestone because Shaft 2 significantly improves overall productivity of the underground development and allows us to move more material, equipment and people between the surface and underground. We have made very good progress in the past few months and completing Shaft 2 provides additional momentum as we move towards a definitive estimate for the development of this world-class ore-body in the second half of 2020."
Read the article online at: https://www.globalminingreview.com/mining/05112019/rio-tinto-hits-milestone-at-oyu-tolgoi/
You might also like
Epiroc breaks ground on new global distribution centre in Sweden
Epiroc AB, a leading productivity and sustainability partner for the mining and infrastructure industries, is breaking ground on a new major distribution centre in Örebro, Sweden. The top-modern facility will be a global hub for Epiroc’s aftermarket products, benefiting customers by enabling a more efficient supply of goods.