Adriatic Metals achieves commercial production
Published by Will Owen,
Editor
Global Mining Review,
Adriatic Metals PLC has achieved commercial production at its Vareš Silver Operation in Bosnia and Herzegovina.
Commercial production has been declared based on maintaining plant throughput levels of 75% over 14 days, including 80% over seven days, and reaching 2000 tpd (90%) in late June.
This milestone follows the resolution of previous constraints related to tailings management. Construction of the Veovaca Tailings Storage Facility (TSF) was completed in March, with initial tailings deposition commencing on 2 April. A dedicated access road linking the Vareš Processing Plant to the TSF was completed and has been operational over the past month.
Mining activities at Rupice are progressing well, with approximately 900 m of underground development completed in 2Q25 (a quarterly record). The plant is performing consistently, and key necessary permits, equipment, and personnel are in place to maintain stable production.
Further details will reportedly be provided in the company’s 2Q25 quarterly activities report.
Laura Tyler, Managing Director & CEO of Adriatic, comments:
“We are proud to announce the achievement of commercial production at the Vareš Silver Operation, marking a significant milestone that demonstrates our ability to operate at production levels that support strong cash generation. I extend my sincere thanks to our entire team and management for their unwavering commitment and effort in achieving this important goal.”
Read the article online at: https://www.globalminingreview.com/mining/01072025/adriatic-metals-achieves-commercial-production/
You might also like
Metso to deliver key process equipment to Twin Hills gold project
Osino Resources Corp. has awarded Metso with an order for the delivery of key process equipment for their Twin Hills gold project in central Namibia.