Akobo Minerals reports operational update
Published by Jess Watts,
Editorial Assistant
Global Mining Review,
Highlights
- Mining operations progressed well in March, starting with lower-grade ore and reaching higher-grade material toward month-end.
- Smelting has been temporarily delayed due to a critical part failure with the electrowinning unit. Ore continues to be mined and stockpiled, and replacement panels are being shipped and will be installed shortly.
- The high-grade ore body at the 575 level, previously referred to as Stope 01, was reached in the final days of March, with an estimated average grade of 75 g/t.
- Work is ongoing to improve camp and site water logistics by connecting wells via pipeline to the water systems at both locations.
- Gold is trading at all-time highs, providing a favourable market backdrop and supporting strong future cash flow.
- While global markets face uncertainty due to tariffs and trade tensions, the gold price remains resilient.
Read the article online at: https://www.globalminingreview.com/finance-business/16042025/akobo-minerals-reports-operational-update/
You might also like
Codelco and Hexagon sign agreement to develop and implement advanced technological solutions in mining
Codelco and Hexagon have signed a Memorandum of Understanding (MoU) that sets the foundation for a strategic partnership focused on exploring, developing, validating, and implementing advanced technological solutions throughout the corporation’s operations.