Akobo Minerals reports operational update
Published by Jess Watts,
Editorial Assistant
Global Mining Review,
Highlights
- Mining operations progressed well in March, starting with lower-grade ore and reaching higher-grade material toward month-end.
- Smelting has been temporarily delayed due to a critical part failure with the electrowinning unit. Ore continues to be mined and stockpiled, and replacement panels are being shipped and will be installed shortly.
- The high-grade ore body at the 575 level, previously referred to as Stope 01, was reached in the final days of March, with an estimated average grade of 75 g/t.
- Work is ongoing to improve camp and site water logistics by connecting wells via pipeline to the water systems at both locations.
- Gold is trading at all-time highs, providing a favourable market backdrop and supporting strong future cash flow.
- While global markets face uncertainty due to tariffs and trade tensions, the gold price remains resilient.
Read the article online at: https://www.globalminingreview.com/mining/16042025/akobo-minerals-reports-operational-update/
You might also like
Jennmar announces partnership with Outokumpu’s Kemi Mine
Jennmar has announced it has entered into a long-term partnership with Outokumpu Corporation, the global leader in sustainable stainless steel, to supply ground control products for the Kemi Mine, the largest underground mine in Finland and Europe’s only operational chrome mine.